Practical resources for project & business professionals

A fictional project example

One question.
A traceable next step.

RFI-007 concerns two drawings that show different pipe routes. This example demonstrates the structure of a record, not a real project decision.

Request reference
RFI-007 · Grid C4
Source documents
Drawing M-102 revision B and detail 4/M-501 revision A
Observed discrepancy
The documents show different routes at the same location.
Question
Which route governs? Please provide the authorized written clarification and its reference.
Current status
Open — awaiting authorized written response.
After a response
Record its source, revision, distribution and any separate change-review requirement.

A recorded question or verbal comment does not authorize a change to the work.